Dr. Jennifer L. Dawson

Assistant Professor

Mechanical Engineering

York College of Pennsylvania

York, PA 17403

Kinsley Engineering Center 106

Phone: 717-815-1520

Fax: 717-849-1621

jdawson1@ycp.edu


Home

Personal

Research

Courses

 

Sanitation Project - Ghana

In September 2009, I joined a team from the York area to serve the community of Apam, Ghana.  The two-week trip was sponsored by Building Solid Foundations, a nonprofit organization working to improve the standard of living in rural Ghana.  During the trip, a team of doctors and nurses performed 220 surgeries and treated approximately 1,200 patients in an outpatient clinic.  Team members helped to plant crops and teach local farmers more productive agricultural techniques.  A team of teachers worked in a school to install a library with books provided through a Rotarty Club grant.  They also did teacher training and distributed school supplies to students.  Finally, I worked with a team to install a sewage treatment system at Apam Catholic Hospital.

Surgeons in the operating room

Chief of Apam touring a newly planted field
Teachers with students

 

 
Doctors and nurses in the outpatient clinic
Simple, low-cost irrigation system
Students and teachers in the new library
 
 

Before we installed the sewage treatment system, Apam Catholic Hospital had a system of open ditches which drained into a field just below the hospital (shown below).  Patients and their families would walk through the sewage before entering the hospital wards, which impacted patient health.  When our team arrived in Ghana we began by determining where we would run the sewage lines.  We then surveyed the site to determine the elevation of the land at points along the pipeline.  Next, I performed design calculations to determine how deep we needed to dig to install the sewage lines.  The design problem had several constraints:  the pipe needed to be at a constant slope despite variations in ground elevation; all points along the pipeline were required to be at least 18 inches below grade; and the dig depth needed to be minimized as it is dangerous to dig narrow ditches more than about 7 feet deep.  Four spreadsheets later, we generated the plot shown below which shows the pipe at a constant slope despite varying ground elevation.  I also created a schematic of the hospital grounds showing the final pipeline with the calculated dig depths at various locations.

 

 


Open sewage ditches at Apam Catholic Hospital


Typical sanitation conditions in Apam


Working with a team member on the pipe design

 

 

  After design work was completed, we began digging trenches to install the pipe.  We used a backhoe to dig 1,300 ft of trenches ranging in depth from 1.5 ft to 6.8 ft, as determined by the design calculations.  We installed 4 in and 6 in diameter, schedule 40 PVC pipe.  Approximately every 60 ft we installed vertical clean outs which are used for system maintenance.  To test the pipeline, we stationed members of the team at each of the vertical cleanouts and then we poured water dyed with Betadine at the top of the system (shown below).  As the water passed by each cleanout, team members cheered!  The water took approximately 7 minutes to travel from the Sister's Convent at the top of the system to the treatment tanks at the bottom.

 

 

Pouring water into the top of the pipeline

 

 

Team members at cleanouts waiting for the water to arrive

 

 

 

Dr. Bob Davis cheering the arrival of the water

 

 

Construction team celebrating a successful test of the pipeline

 

 

  While part of the team worked on the pipeline, others moved the four tanks comprising the sewage treatment system and installed them on concrete pads (shown below).  The treatment system is manufactured by Cromaglass of Williamsport, PA.  Cromaglass donated half the cost of the system and sent two engineers to Ghana to perform the installation and testing.  The only byproduct of the Cromaglass system is water that can be used for irrigation.  It was necessary to run a new electrical line to the treatment site and subsequent testing was conducted to ensure the system's pumps and sensors worked properly.  The system is connected to the hospital's internet, allowing Cromaglass to monitor the system from Williamsport and advise the hospital staff on maintenance and repair procedures.

 

 

Moving a tank using a tractor

 

 

Final step of moving the tank onto its concrete pad

 

 

 
All tanks installed
 

 

Completed tank installation

 

 
  This project was challenging and rewarding.  Each day we faced obstacles, whether it was language barriers, a backhoe requiring maintenence, difficulty in obtaining additional PVC pipe components, or wheelchairs and gurneys needing to pass through our work zone.  Despite the set-backs, our team worked cooperatively and supportively to achieve remarkable results in only 12 days.  The people of Apam showed us extraordinary hospitality and dedicatedly partnered with us in all of our work.  I am deeply grateful to have had the opportunity to travel to Ghana, to contribute to the project, and to build relationships with such warm and gracious people.

 

 
Team of Ghanians who worked with us at the hospital
 
View from Elmina Castle, hub of the slave trade (Cape Coast)
 
Kids visiting our worksite
 
 
People of Apam singing and dancing at our team welcome ceremony
 
Kids in Apam
 
Beautiful beach near Cape Coast